Another alternative, successful at Manzanita Village of Prescott, was having the common house first -- before members moved in. It became a gathering place for people who would soon be living in the Village; indeed, communication with those yet to live here is still an important feature of our common house. So, building the common house BEFORE complete move-in is a strong recommendation from us here. Sarah D. . _______________________________________________ Cohousing-L mailing list Cohousing-L [at] cohousing.org Unsubscribe and other info: http://www.communityforum.net/mailman/listinfo/cohousing-l
- Re: Common House Construction Sequencing, (continued)
- Re: Common House Construction Sequencing Elizabeth Stevenson, October 17 2001
-
RE: Common House Construction Sequencing Maggie, October 18 2001
- Separating the Common House (was construction sequence) Robert P. Arjet, October 18 2001
- Re: Separating the Common House (was construction sequence) Sharon Villines, October 18 2001
-
Request: Operating Agreements Robert P. Arjet, October 19 2001
- Re: Request: Operating Agreements Margaret Weatherly, October 20 2001
- RE: Request: Operating Agreements Rowenahc, October 23 2001
Results generated by Tiger Technologies Web hosting using MHonArc.