Re: cost estimates
From: Diana E Carroll (dianaecarrollgmail.com)
Date: Tue, 16 Feb 2010 05:23:20 -0800 (PST)
Marganne asks:

Why is it acceptable to have someone charge you more money than what
you originally agreed upon?

It's not that simple.

First, when you say "cost overrun", you mean relative to what? The agreed upon contract price from the builder? That's not where our "overruns" happened. Here's what happened to us:

1 - long long before we found land or decided on the specifics of the community, we developed a target budget for how much the homes would cost, based on what people could afford and with guidance from Chris ScottHanson, a cohousing professional. We presented that target budget to new potential members who decided whether to buy in based in part on whether those hypothetical prices were affordable for them

2 - our land search took much, much longer than we expected (7 years) and involved costs with various professionals (our professional CSH, architects, engineers for feasibility, etc) not to mention ongoing costs for marketing, legal, etc. These sunk costs get added to the budget, raising our target prices.

3 - Eventually we found land. We did a VERY PRELIMINARY feasibility study to determine if the land would work and get an idea what building would cost and adjusted our budget, again with CSH's help...the budget went up, of course. I don't know why the budget in step 1 wasn't or 2 wasn't enough -- part of it was mis-estimation, part of it was because the actual land we found had some complicated aspects of development that we hadn't anticipated, some is because the cost of labor and materials had increased over those 7 years. Some of the folks who bought in when the budget was at stage 1 above were now priced out. Is this a "cost overrun"?

4 - We hired engineers and architects and began the long process of actually figuring out what the community would look like. We had our target budget from step 3 above in mind. We made out plans and submitted them to builders for bids, and the bids were far higher than we had wanted. Why? In part we set our sights to high. But in LARGE part is was because we had used a too low "cost per foot" estimate for construction. We went through the painful process of letting go of some of what we wanted to lower the costs (a process called, ironically, "value engineering"), and also raised our prices...again pricing out people who had thought our price point would be lower. Is this a "cost overrun"?

5 - we selected a builder with a fixed contract price. Over the 2-3 years of construction, we found there were various things that needed to be changed -- stuff we forgot, aspects of the land we didn't know about until construction started, things we were forced to add by various town and state officials...these were "change orders" to the original contract that raised the cost. Plus there were WAY more "soft costs" (non-construction costs -- legal fees, consulting fees, architects, engineers, marketing, etc.) than anyone had anticipated. So...we raised our budget AGAIN. Again we lost people due to the price increase.

In the end the cost of our homes was about DOUBLE what the original target price was in step 1. I don't know whether this qualifies as a "cost overrun" by your definition, but it is definitely part of what people mean when they talk about "spiraling costs", and very little of it came down to what you described as thinking it was "acceptable to have someone charge you more money than what you originally agreed upon"

- Diana
--
Now is the time for community........Mosaic Commons cohousing
Homes still available...........http://www.mosaic-commons.org

Results generated by Tiger Technologies Web hosting using MHonArc.