Re: Reserve Study Redux...
From: Lyle Scheer (wonkomonkeyhouse.org)
Date: Fri, 25 Aug 2006 10:55:19 -0700 (PDT)
-----BEGIN PGP SIGNED MESSAGE-----
Hash: RIPEMD160

Sharon Villines wrote:
> On Aug 25, 2006, at 12:22 PM, Lyle Scheer wrote:
> 
>> Having a reserve study done by an expert would provide that once, but 
>> at
>> what stage of construction?  I'd personally want a concrete "expert" to
>> look over the slabs the day they are poured for things that can be
>> addressed before it sets, framing expert to look over exposed framing
>> before it gets covered, etc.
> 
> Where are you? Sorry, but I can't keep track.

Ashland, Oregon.

- - Lyle